Drilling rig beneath a stormy sky.
CS 117
North America
CANADA
Scale Removal
Vertical
Perforations
Carbonate

Oil production up 716% in the first month

A scaled perforated interval in Canada’s Slave Point formation was treated during a workover. Oil production rose 716% over the first month and held 258% higher over three months.

A scaled perforated interval in Canada's Slave Point formation was treated during a workover. Oil production rose 716% over the first month and held 258% higher over three months.

Key results

  • Perforated Intervals
  • 716% increase in average oil production over 1-month
  • 258% increase in sustained production over 3-months

Challenge

Client determined that a reduction in total oil production from a producing well was due to scaling of a perforated interval in the Slave Point production zone. Indications of calcium carbonate (CaCO3) on both tubular and bottom hole pump were determined as the cause of the decreasing production.

Client required a cost effective remedial solution, in conjunction with a work over, to increase production. Client was seeking to deploy a technology that is simple, and that deals directly with the root cause of the decline – scaling and near-wellbore formation damage.

  • Slave Point limestone
  • Depth: 1800 m (5900 ft)
  • Temperature: 45 °C (113 °F)
Average Oil Rate (b/d), CS 117.

Solution

Electro-hydraulic stimulation in cased hole applications.

  • Wireline deployed in conjunction with a workover on a producing well.
  • Completed BLUESPARK® treatment over the perforated zone of interest that had suspected scaling: Slave Point formation (dolomite/limestone).
  • BLUESPARK® treated the perforated interval of approximately 2.5 m (8 ft).
  • Ran production tubing and pump assembly into wellbore, monitoring production rates, pressures and fluid levels over the course of 90 days.

Outcome

  • Significant inflow of oil was produced after the remediation.
  • Client data shows an average oil production of 36.7 b/d over a one-month period (716% increase).
  • Sustained production over 90 days averaged 16.1 b/d of oil (258% increase).
  • Client is now evaluating the use of electro-hydraulic stimulation in other tight oil reservoir environments within the production pool for remedial interventions, in conjunction with workovers.

Talk to our experts

Let's Go

Discover our tools

Let's Go