Gas production up 300%, still up 280% after a year

Gas production increased 300% over a three-month comparison following BLUESPARK treatment.

Gas production increased 300% over a three-month comparison following BLUESPARK treatment.

Key results

  • Perforated Completion
  • 8 hours total treatment time for 20ft interval
  • 300% increase in gas production (3-month comparison)
  • Sustained Results 280% increase in gas production 12-months post treatment

Challenge

The client’s well was fracked when it was completed, and flowed as high as 900 MCF/d of wet CBM gas. Within 2 years, the gas production rate had dropped by 75%. Several acid treatments were done over the next few years, usually resulting in an increase from 50% – 100% that would last 2 to 4 months. The client decided to try a BLUESPARK® treatment to see if better results could be obtained.

  • Depth: 4,700 ft (1,430 m)
  • Ferron coal-bearing sandstone
Gas Production, MCF/d, CS 126.

Solution

Improve connectivity to the reservoir by clearing out blockages using electro-hydraulic stimulation technology.

  • The wellbore was cleaned by a bit & scraper run.
  • The BLUESPARK® tool was run on third-party E-Line to the perforated intervals.
  • Four perforated intervals of 20 ft total (6 m) were treated in less than 8 hours of total operating time with our wireline conveyed tool to improve flow through the formation rock.
  • The well was put back on production and monitored.

Outcome

  • The well saw an immediate increase in gas production, which continually rose over the next 3 months.
  • The average gas production increased from 17 MCF/d to 71 MCF/d in a 3-month comparison, an increase of over 300%.
  • The average gas production for the 12-months post-BLUESPARK® was 65 MCF/d, a 280% increase over the pre-BLUESPARK® rate.