Jack-up drilling rig.
CS 131
North Sea
Scale Removal
Offshore Platform
Tubulars
P&A

Scale cleared for P&A without coiled tubing, 8 days saved

Complete scale removal with BLUESPARK saved eight days compared with the planned coil operation.

Complete scale removal with BLUESPARK saved eight days compared with the planned coil operation.

Key results

  • Targeted Treatment Caliper Confirmation of clean intervals
  • 48 hours total operating time
  • CaCO3 scale completely removed
  • 8 days saved vs. using planned coil operation
scale removal treatment results, CS 131

Challenge

A Major North Sea operator requires Calcium carbonate scale (CaCO3) to be removed from sections of tubing for plug set and tubing cut prior to pulling the completion. Calcium carbonate scale (CaCO3) forms inside the tubing and is very difficult to remove using mechanical or chemical methods. This objective was previously achieved from a jack-up rig using coiled-tubing and jetting technology (fluids & abrasives).

The operator had previous success using BLUESPARK® to remove scale from other completion hardware, so decided to use BLUESPARK® to clean sections of the tubing.

  • Treatment Depth: 5,800 ft (1,770 m)
  • Treatment interval @ 30° deviation

Solution

Remove CaCO3 scale from sections of tubing using electro-hydraulic stimulation technology.

  • The BLUESPARK® tool was deployed on the operator’s preferred wireline provider’s E-Line from the platform, prior to the jack-up’s arrival.
  • A Fluid Hold-Up Tool (FHUT) was used to maintain a fluid column over the toolstring.
  • Two 20 foot intervals (6 m) were treated in one wireline run in less than 4 hours of treatment time. Total operating time was 48 hours.
  • A caliper log was performed on wireline to verify the scale removal.

Outcome

  • The caliper log confirmed that the BlueSpark had completely removed the CaCO3 scale from the inside of the tubing over the two treated sections.
  • The plug was successfully set and pressure tested, followed by a successful tubing cut, both in the zones treated by BLUESPARK®.
  • Coiled Tubing was not required, eliminating the cost of that service – mobilisation, rig-up, rig-down and reduced crew.
  • Reduction of 8 days of jack-up rig time, as the BLUESPARK® operation was performed offline.