Offshore drilling rig near a wooded coastline.
CS 145
North Sea
NORWAY
Scale Removal
Offshore Platform
SSSV
P&A

Targeted treatment of the ASV

BLUESPARK treated a 25 m interval across an annular safety valve. Caliper logs confirmed 80-100% scale reduction; up to five days and USD 200K were saved.

BLUESPARK treated a 25 m interval across an annular safety valve. Caliper logs confirmed 80-100% scale reduction; up to five days and USD 200K were saved.

Key results

  • Run on E-Line
  • 14 hours operating time
  • Up to 100% in scale reduction confirmed by MFC log
  • 5 days & $200K saved
scale removal treatment results, CS 145
scale removal treatment results, CS 145

Challenge

A major operator on the Norwegian Continental Shelf needed to release the annular safety valve (ASV) of a well for later completion string retrieval but were concerned about scale buildup. Normally they would use string shots and brushes to remove scale, or, they would cut the tubing & the ASV.

They elected to try BlueSpark pulsed power technology to remove the scale instead, as it can more accurately target specific depths and would save both time and cost.

  • Depth: 525 m (1,720 ft)
  • Temperature: 40 °C (104 °F)

Solution

Remove scale from the upper completion of the wellbore using electro-hydraulic pulsing technology.

  • The BLUESPARK® tool was run on third-party E-Line to the treatment interval.
  • A 25 m interval was treated across the ASV and below it, thereby exposing the internal “punch tool locator” profile and clearing an area for plug installation.
  • The treatment was completed in one run in less than 14 hours of operating time.
  • A multi-finger caliper (MFC) was run over the treated and untreated sections of the wellbore for comparison to the previous caliper log.

Outcome

  • The MFC log confirmed that the scale over the interval treated had been reduced by 80 – 100%.
  • The plug was set below the ASV and the ASV was released with a dedicated punch tool.
  • BLUESPARK® saved up to 5 days of operating time and USD 200K.

“I have had a belief in the BLUESPARK® tool for some time, and it was good to finally deploy and see for ourselves. We were pleased to have tools and personnel mobilized on short notice and have the BLUESPARK® tool successfully remove scale during the operation.”

Team Lead, Well Operations