Crew members wearing hard hats beside a pipeline.
CS 155
North America
USA
GEOTHERMAL
Producing Well
Vertical

Geothermal well brought back online

BLUESPARK treated a 105 ft interval in a geothermal well in eight hours. Well production increased 134%.

BLUESPARK treated a 105 ft interval in a geothermal well in eight hours. Well production increased 134%.

Key results

  • 8 hours treatment time
  • 105 ft. interval treated
  • 134% increase in well production
  • Run on E-Line

Challenge

The Town of Lakeview utilizes a geothermal district heating system to heat local schools, the community hospital, the emergency services station, and a dental clinic. The system experienced a severe decrease in heat generation due to a 45% decrease in flow rate from the production well due to the build-up of goethite scale.

  • Vertically drilled
  • Open Hole completion
  • Igneous reservoir (basalt, ash)
  • Depth: 700 ft (213 m)
  • Temperature: 88 °C (190 °F)
Geothermal Production, CS 155.

Solution

Improve flow from the reservoir into the geothermal production well by removing goethite scale using electro-hydraulic pulsing technology.

  • The BLUESPARK® 275 tool was run on a partner’s E-Line to the treatment interval
  • Three intervals for a total of 105 ft (32 m) were selectively pulsed in a treatment time of 8 hours
  • The well was placed back on-line immediately post the Blue Spark treatment

Outcome

  • The well production rate was increased 134% to 206 gpm (13.0 l/s), above the minimum required production rate of 130 gpm (8.2 l/s)
  • Buildings that had to be shut down due to lack of heat are now operational