NAM-IW-128 (Canada West)
CHALLENGE
A 5 year old disposal well was experiencing reduced injection rates and increased injection pressure. Over a 2 year period, 20 stimulations were conducted, averaging one treatment every 33 days.
The client was looking for a cost effective treatment that would:
improve the injection rate
decrease the injection pressure
reduce stimulation frequency
SOLUTION
The BLUESPARK® tool was deployed through tubing on third-party E-Line and completed in 8 hours.
Post BLUESPARK® customer chemical treatment conducted.
5X more effective than historical stimulation average.
CONDITIONS
McMurray Sandstone
Depth 500 m (1600 ft)