Case Studies

NAM-IW-133 (Canada West)

Both wells saw an immediate drop in injection pressure resulting in an increase in injection rate. Step rate tests done immediately after the treatment and after several months confirmed lower pressures and higher injection rates than before the treatment were being maintained.

Read More

NAM-IW-122 (Canada West)

Client data from the BLUESPARK® treated well showed over 20x increase in injection rate and 45% reduction in injection pressure. 6 months later this well injects between 60 to 90 bbl/d and pressure is at 4200 kPa.

Read More

NAM-SR-119 (USA Permian)

The client ran back in the wellbore with tubing and discovered that the BLUESPARK® had created 11 feet of fill (in 7 inch casing). An analysis of the fill determined the presence of silica and clay, along with the BaSO4, confirming that the perf tunnels had been cleaned.

Read More